Mongabay-India

A centralised power market will help in savings, support green energy producers, hints study

Chennai cityscape. Photo by VtTN/ Wikimedia Commons.
  • India’s proposed national centralised electricity market has the potential of savings costs of up to Rs 1.5-4 crore per day for distribution companies, according to a study in Maharashtra and Tamil Nadu.
  • The Ministry of Power, earlier in 2021, had proposed the concept of this centralised electricity market called Market Based Economic Dispatch (MBED) and planned to implement it in a phased manner, but it is yet to kick off.
  • Experts claimed that the new model hints at savings and increased benefits to renewable energy generators but is mired with several challenges that can prove a hurdle in this transition.

A recent study by RMI, an international clean energy think tank, analysed the potential of India’s proposed centralised electricity market in Maharashtra and Tamil Nadu and found increased prospects of financial savings for distribution companies.

The centralised electricity market concept, referred to as the Market-Based Economic Dispatch (MBED) mechanism, proposes a centralised, national electricity trading market, under which all the participating electricity generators can pool their power under a single market. India currently operates under a decentralisled electricity market in which the electricity distribution companies (discoms) have long-term Power Purchase Agreements (PPAs) with selected power generators from whom they purchase power at a majority of their power requirements at a fixed price.

Discoms are financially distressed and collectively owe more than Rs. 1000 billion ($12.3 billion) in debt, resulting in delayed payments to generators, inadequate investment in grid infrastructure, and insufficient resources for effective operations, notes the study. “This contributes to the financial risk faced by renewable generators. A fiscally healthy distribution sector and robust renewable growth are vital for India to meet its rising electricity demand and NDC targets,” the report says.

A windfarm in Maharashtra. Photo by Phadke/ Wikimedia Commons.
A windfarm in Maharashtra. A fiscally healthy distribution sector and robust renewable growth are vital for India to meet its rising electricity demand, finds a recent study by RMI, a clean energy think tank. Photo by Phadke/ Wikimedia Commons.

With the MBED mechanism, discoms have the advantage of a bigger pool of generators to source power for distribution, likely at a lower price owing to the competition. The MBED mechanism uses the Day-Ahead-Market (DAM) method, in which generators and discoms trade electricity through auctions and bidding, a day ahead of the scheduling of electricity by the discoms for consumers.

Study of the power system of two states

In its analysis of savings through MBED, RMI studied the possibility of cost savings for discoms when the surplus capacity of electricity production is reallocated under MBED.

It considered the daily generator-level data on the variable and fixed costs. The capacity of generation and actual generation between July 15 and August 15 of 2022 is considered peak demand season, and December 15 to January 15 is regarded as an off-peak demand season. It also determined the joint variable costs of the two states under the existing case when the actual generation takes place.

To find out the savings per day, the researchers found the difference in cost under the existing case and the price under a pooled case. “The empirical analysis utilises generator-level data on costs, declared capacity, and actual generation for plants for two historical periods representing peak and off-peak demand seasons. Our analysis reveals potential savings of Rs. 1.5 to 4 crores ($184,000 to $491,000) per day across peak and off-peak seasons or 2.8% to 7.0% annual savings…respectively,” the report said.

Air conditioning units in a commercial block in Mumbai. Photo by David Brossard/ Wikimedia Commons.
Air conditioning units in a commercial block in Mumbai. Photo by David Brossard/ Wikimedia Commons.

However, though the government has conducted some pilot projects and planned to implement MBED in a phased manner from April 1, 2022, there are some logistical and other challenges, keeping it from taking off.

“Market transitions are not easy even in a developed economy. It is a gradual step and takes time and due deliberations. It took time to slowly transition into it, even in advance countries where it has been tried. The Indian power sector had legacy issues. Different states and discoms have different situations altogether. Some are cash-strapped and struggling. Replication of successful models of market transition from other countries as it is not rational as the geographies and challenges are different. It needs to be an inspiration, but India specific solutions to forward market transition are needed,” said Jagabanta Ningthoujam, Principal (Power Sector) at RMI India.

Advantages and challenges of MBED

The Central Electricity Regulatory Commission (CERC), earlier in 2018, issued a discussion paper on the issue of MBED and sought views from different stakeholders. The Ministry of Power in 2021 also issued another framework for implementing the MBED market and batted for initiating the new national-level wholesale electricity market in a phased manner. Phase I, which was slated to start on April 1, 2022, was meant first to cover selected thermal power plants.

“Ministry of Power recognized the need for a consensual and phased approach in implementing MBED that will help participants, power exchanges and load despatch centres to adapt gradually to the new regime…The Ministry of Power noticed substantial alignment amongst all key stakeholders on a phased approach and the process to implement Phase 1 of MBED, starting with the mandatory participation of the Inter-State Generating Stations. Generation plants of others can also participate in Phase 1 voluntarily,” a statement from the power ministry said.

The RMI report claimed that the long PPAs of the discoms prevent them from getting the full benefits of the declining generation costs of renewables. These long PPAs, which are for around 25 years, could be more flexible, limit discoms to purchase low-cost power, and affect their financial viability as they often are forced with high fixed charge payments for inefficient plant capacity minimally used. The report claimed that inefficient power procurement usually raises the national average power purchase cost, increasing 13 percent between 2015-16 and 2021-22.

A windfarm and transmission network in Tamil Nadu. The RMI report stated that the long PPAs of the discoms prevent them from getting the full benefits of the declining generation costs of renewables. Photo by Priyanka Shankar/Mongabay.
Wind turbines and transmission network in Tamil Nadu. The RMI report stated that the long PPAs of the discoms prevent them from getting the full benefits of the declining generation costs of renewables. Photo by Priyanka Shankar/Mongabay.

It also added that many renewable energy generators are also at financial risk as their power is often curtailed due to insufficient grid availability and other technical reasons. Under the MBED market these power generators will have more opportunity to sell.

Other experts claimed that implementing the new market regime is also mired with challenges to the discoms. Ann Josey from Prayas Group from Pune said that one of the significant impacts under such a system could be on the discoms too. Several discoms in India are financially strapped and suffer from several vulnerabilities.

“There are multiple risks with the proposal of mandating MBED. The need for upfront payment will strain discom finances. As transmission charges are unaccounted in the price discovery, Discoms may not have savings. The proposed mechanism assumes the discoms are adept traders which may not be the case. Pilots and studies to assess savings, risks are needed before this scheme is launched,” Josey told Mongabay-India.

The report recommended that for the success of the MBED market, the government needs to propose a robust transition plan giving details on the structures and responsibilities of the different stakeholders, make a public data portal to assess the wholesale electricity market operations, update the transmission planning process and develop a roadmap for the complementary wholesale market to increase the benefits under the MBED mechanism.


Read more: Decentralised solar is transforming rural India, needs extra push


 

Banner image: Chennai cityscape. Photo by VtTN/ Wikimedia Commons.

Exit mobile version